Columbian Square Improvement Project News & Announcements

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Anticipated Construction Schedule: May 13 – May 17, 2024

Beginning Monday, May 13, 2024, the Contractor is scheduled to begin preparing and forming the new concrete sidewalks on the east side of... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Anticipated Construction Schedule: May 6 – May 10, 2024

On Monday, May 6, 2024, the Contractor is scheduled to begin preparing and pouring concrete sidewalks from the Cameo Theater to Fogg Road.... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Anticipated Construction Schedule: April 29 – May 3, 2024

Beginning on Monday, April 29, 2024, the Contractor is scheduled to continue the installation of street lighting conduits on Columbian... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Anticipated Construction Schedule: April 22 – 26, 2024

Beginning on Monday, April 22, 2024, the Contractor will be working on the installation of street lighting conduits and light pole bases.... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Anticipated Construction Schedule: April 15 – 19, 2024

On Monday, April 15, 2024, the Contractor will be installing new site lighting conduits, starting at Chauncy Street and working through to... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Anticipated Construction Schedule: April 8 – 12, 2024

On Monday, April 8, 2024, the Contractor will start pouring new concrete sidewalks on Pleasant Street (on both sides of Tower Avenue), this... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Anticipated Construction Schedule: April 1 – 5, 2024

Beginning on Monday, April 1, 2024, crews will be working at the intersection of Columbian Street and Burton Terrace, and also on Pleasant... more ››

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: March 25-29, 2024

Columbian Square Improvement Project Anticipated Construction Schedule: March 25 – 29, 2024

Beginning on Monday, March 25, 2024, the Contractor is scheduled to continue with the installation of the curbing and sidewalks on both... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: March 18 – 22, 2024

Beginning on Monday, March 18, 2024, the Contractor is expected to return to the project area and will be removing and resetting curbing on... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Anticipated Construction Schedule: January 2024

Beginning on Monday, January 8, 2024, the Contractor is anticipated to begin scaling back on construction activities for this month due to... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: January 2 – 5, 2024

No work is scheduled for Monday, January 1, 2024, in observation of New Year’s Day.

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: December 25 – 29, 2023

No work is scheduled for Monday, December 25, 2023, in observation of Christmas. Beginning on Tuesday, December 26, 2023, the Contractor is... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: December 18 – 22, 2023

Beginning on Monday, December 18, 2023, the Contractor is anticipated to continue working on site lighting and traffic signal underground... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: December 11 – 15, 2023

Beginning on Monday, December 11, 2023, the Contractor is scheduled to continue sidewalk preparation work on the east side of Columbian... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: December 4 – 8, 2023

Monday, December 4, 2023: The Contractor is scheduled to install sidewalk curbing starting at the intersection of... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: November 27, 2023 – December 1, 2023

Beginning on Monday, November 27, 2023, the Contractor is scheduled to begin excavating for full depth asphalt replacement near the... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: November 20 – 22, 2023

Between Monday and Wednesday (11/20/2023 – 11/22/2023), roadway paving work will continue to take place on Columbian Street, between Fogg... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule

Beginning on Monday, November 13, 2023, construction crews are scheduled to complete permanent asphalt patching at the intersection of... more ››

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: November 4–10, 2023

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: November 4–10, 2023

Saturday, November 4, 2023Construction crews are scheduled to begin roadway paving on Columbian Street from 7:00AM to 3:30PM.

Columbian Street Roadway Paving

Columbian Street Roadway Paving Scheduled for Saturday November 4, 2023

The construction schedule for the Columbian Square Improvement Project has been altered, construction crews are scheduled to begin roadway... more ››

Pages