What are the decision timelines for the Board?

The Board must make a decision within the following statatory timeframes unless otherwise extended by mutual agreement between the applicant and the Board:

  • Special Permits - no later than 90 days after the close of the public hearing
  • Variances - no later than 100 days from the application filing date

Click to view the Variance Flow Chart.

Click to view the Special Permit Flow Chart.