Columbian Square Improvement Project News & Announcements

Image of Weekly Anticipated Construction Schedule: June 19 – 23, 2023

Weekly Anticipated Construction Schedule: June 19 – 23, 2023

Construction Work Hours: Monday – Friday, 7:00AM – 4:00PM

Work Zone: June 12-16, 2023

Weekly Anticipated Construction Schedule: June 12 – 16, 2023

On Monday, June 12, 2023, PA Landers will deploy two crews in the project area. The first crew will continue drainage work at the... more ››

Image of Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: June 5 - 9, 2023

On Monday, June 5, 2023, PA Landers will continue drainage work at the intersection of Union Street and Camelot Way. It is anticipated that... more ››

Image of Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: May 29 - June 2, 2023

PA Landers will observe the Memorial Day Holiday on Monday, May 29, 2023. On Tuesday, May 30, 2023, PA Landers will begin to remove the... more ››

Image of Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: May 22 - 26, 2023

On Monday, May 22, 2023, PA Landers will begin the installation of National Grid primary electric vaults at the corner of Pleasant Street... more ››

Detour – Northbound Union Street Traffic at Central Street

In an effort to streamline traffic flows through the area, it was necessary to implement a detour of northbound traffic from Union Street... more ››

Weekly Anticipated Construction Schedule May 15 - 19, 2023 Image

Weekly Anticipated Construction Schedule: May 15 - 18, 2023

On Monday, May 15, 2023, PA Landers will continue installing drainage on Union Street between Pleasant Street and Camelot Way. Due to the... more ››

Image of Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: May 8 - 12, 2023

On Monday, May 8, 2023, PA Landers will perform drainage work in the northbound lane of Pleasant Street between Main Street and Wilbur... more ››

Image of Detour Map

A Temporary Detour of Pleasant Street has been Implemented Between Tower Avenue and Torrey Street

Due to the location of the utilities on Pleasant Street, it will be necessary to implement a temporary detour of roadway traffic from... more ››

Weekly Anticipated Construction Schedule May 1 - 5, 2023 Image

Weekly Anticipated Construction Schedule: May 1 - 5, 2023

On Monday, May 1, 2023, PA Landers will perform a test pit to verify utilities and perform drainage work in the northbound lane of Pleasant... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: April 24th – 28th, 2023

On Monday, April 24, 2023, PA Landers will continue to install drainage system upgrades on Pleasant Street between C.C. Shepherd Funeral... more ››

Decorative image of the Weekly Anticipated Construction Schedule for April 17 - 21, 2023

Weekly Anticipated Construction Schedule - April 17 - 21, 2023

On Monday, April 17, 2023, PA Landers will begin to install an 8” water insertion valve on Pleasant Street across from the intersection of... more ››

Image of Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule - April 10 - 14, 2023

PA Landers will begin drainage upgrades on Pleasant Street at the intersection of Tower Avenue and work southeast towards Columbian Square... more ››

Image of Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule - April 3 - 7, 2023

Planned Construction Activities:

Image Construction Season Has Arrived

Construction Season has Arrived!

Construction activities are anticipated to begin on Monday, March 27, 2023, at 7:00 AM barring any unforeseen conditions or weather-related... more ››

#ColumbianSqCornerstones

Announcing the Columbian Square Cornerstones Campaign

Weymouth’s Mayor Robert Hedlund and the Weymouth Planning & Community Development Department recognize that businesses located within... more ››

Drainage Construction Anticipated to Begin Early December

Drainage Work is Anticipated to Begin in Early December

The contractor for the Columbian Square Improvement Project, PA Landers is anticipated to perform drainage improvements on Pleasant Street... more ››

Recording Pre-Construction Conditions

Recording of Pre-Construction Conditions of Columbian Square Scheduled for November 15, 2022

On Tuesday, November 15, 2022, weather permitting A & B Photography, LLC will be on site to begin recording pre-construction conditions... more ››

Columbian Square Improvement Project Virtual Meeting – Monday, December 13, 2021

Due to technical issues, the virtual webinar portion of the December 7, 2021 Columbian Square Improvement Project Neighborhood meeting was... more ››

Columbian Square Project

Columbian Square Improvement Project Neighborhood Meeting – December 7, 2021

Big changes are on the horizon for Columbian Square! We hope that you can join us to learn more about the design for Columbian Square on ... more ››