Columbian Square Improvement Project News & Announcements

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: October 23 – 27, 2023

Beginning on Monday, October 23, 2023, construction crews are anticipated to conclude full-depth roadway reconstruction work, starting near... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: October 16 – 20, 2023

Beginning on Monday, October 16, 2023, construction crews are anticipated to resume the full-depth roadway reconstruction of Pleasant... more ››

Weekly Anticipated Construction Schedule

Columbian Square Improvement Project Weekly Anticipated Construction Schedule: October 10 – 13, 2023

Beginning on Tuesday, October 10, 2023, construction crews are anticipated to begin the excavation for full-depth roadway reconstruction of... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: October 2 – 6, 2023

Beginning on Monday, October 2, 2023, construction crews will begin working the installation of conduit for the new street lighting. Work... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: September 25 – 29, 2023

Monday, September 25, 2023, through Tuesday, September 26, 2023, construction crews will continue working on the installation of traffic... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: September 18 – 22, 2023

During the week of September 18, 2023, construction crews will continue working on the installation of traffic signal conduits at the... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: September 11 – 15, 2023

Between Monday September 11th and Tuesday, September 12th, construction crews will continue working on water service improvements at the... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: September 5 – 8, 2023

In observance of the Labor Day holiday, no construction will be taking place on Monday, September 4, 2023.

Weekly Anticipated Construction Schedule: August 28 – September 1, 2023

On Monday, August 28, 2023, construction crews will continue with the installation of primary electric conduits at the intersection of... more ››

Updated Construction Schedule for the week of August 21 – 25, 2023

Beginning on Tuesday, August 22, 2023, construction crews will mobilize to the intersection of Fogg Road and Columbian Street to work on... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: August 21 – 25, 2023

Beginning on Monday, August 21, 2023, crews will be working on water service improvements at the intersection of Tower Avenue and Pleasant... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: August 14 – 18, 2023

Beginning on Monday, August 14, 2023, construction crews will continue with the installation of primary electric conduits at the... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: August 7 – 11, 2023

Beginning on Monday, August 7, 2023, construction crews will continue with the installation of primary electric and communication conduits... more ››

Pleasant Street Westbound Detour - August 3, 2023

Between the hours of 7:00 AM and 2:00 PM on Thursday, August 3, 2023, the contractor PA Landers will be performing a water main service... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: July 31 – August 4, 2023

Beginning on Monday, July 31, 2023, construction crews will continue with the installation of primary electric and communication conduits... more ››

Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: July 24 – 28, 2023

Beginning on Monday, July 24, 2023, construction crews will continue with water main work at the intersection of Fogg Road and Columbian... more ››

Weekly Anticipated Construction Schedule: July 17 – 21, 2023

Beginning on Monday, July 17, 2023, construction crews will continue upgrading water services lines near the intersection of Fogg Road and... more ››

Image of Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: July 10 – 14, 2023

Construction Work Hours: Monday – Friday, 7:00AM – 4:00PM

Image of Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: July 3 – 7, 2023

Construction Work Hours: Monday – Friday, 7:00AM – 4:00PM

Image of Weekly Anticipated Construction Schedule

Weekly Anticipated Construction Schedule: June 26 – 30, 2023

Construction Work Hours: Monday – Friday, 7:00AM – 4:00PM